No Client Agent / Main Contractor Description Years
14 Pahlawan Power Sdn Bhd ExPG To supply & Deliver of Steam Turbine & Transformer’s Spare Parts for a 330MW Combine Cycle Gas Turbine 2013
15 Air Products (M) Sdn Bhd ExPG Site  Repair, Modification and Maintenance Works for Convention Box, Tube Bundle Heat Exchanger and Analysers at Air Products West Port During Planed Outage 2013
16 Red Energy Sdn Bhd ExPG Mobilization of Labour and necessary tools and equipment to carry out hydrotest including liaising with DOSH for Vertical Air Receiver. 2013
17 N.U.R Power Generation Sdn. Bhd. WEIR Engineering Services Ltd Electrical System Associated Auxiliaries Works for MH06114 Kulim Combined Cycle Block 2 Re-commissioning works. 2012
18 Air Products (M) Sdn Bhd ExPG Major outage on various Mechanical & E&I Job at Air Products West Port & KLK2 2012
19 Pahlawan Power Sdn Bhd ExPG Supply Of TakaokaTransformer Spares Dial Type Oil Lvl Indctr For Main Tank 2012
20 Tunku Jafar Power Plant (PD Power) Bumi Teknikal Solution Sdn Bhd Supply of 3C Rectifier modules for cathodic protection system 2012
21 Petronas Cari Gali EP Engineering Supply of Grundfossubmersible pump 2012
22 First Gen Corporation WEIR Engineering Engineering & Programing Consultation For 55MW Steam Turbine Controller System For Bacon-Manito (BacMan) Geothermal Power Plant,PH 2012
23 N.U.R Power Generation WEIR Engineering 12 Month Warranty Services of Electrical & Instrumentation Installation Works For 220MW Combine Cycle Steam Turbine Nur Power  2012
24 AboitizPower Corporation WEIR Engineering Instrumentation & Control System Consultation & Supervision Services for 63.2 MW Steam Turbine for Makiling- Banahow (MakBan) Geothermal Power Plant 2012
25 Tunku Jaafar Power Station (1500 MW) Bumi Teknikal Solution Sdn Bhd  Supply & Deliver of Measurement Module at Thor Panel for PD1 Cooling Water System’s Cathodic Protection. 2012
26 L.V Technology Ltd (Thailand) ExPG Obtain Design Approval and Certificate of Fitness From Dosh Including Hydrotest For 2 Units of Vessels. 2012
27 Air Products (M) Sdn Bhd ExPG To Supply Labour, Tools, Submission of Procedures to Conduct Leak Test at Steam Drum and Convection Box and dismantle & installation of Syngas Header at Air Product, West Port. 2011
28 YTL Power Services ExPG To Design, Supply and Install A New Control Panel for the Existing Impressed Current Cathodic Protection System at YTL PAKA.  2011
29 N.U.R Power Generation Sdn. Bhd.  WEIR Engineering Services Ltd E&I Package for MH06114 Kulim Combined Cycle Block 2 Re-commissioning works. 2011
30 Boustead Penang Shipyard Sdn Bhd ExPG Design, Supply, Fabricate & Insallation of Hoisiting System for a Manufacturing Plant on Lot 10 in Bentong Industrial Park Phase 2B. 2010
31 Jutasama Sdn Bhd ExPG Supply and Installation of Complete E&I Works for PSA Unit for HPU-1 Revamp. 2010
32 Tepat Teknik Sdn Bhd ExPG To Supply Labour, Materials, Tools and Equipment To Carry Out Cabling  and Termination Works for Control Valves in accordance with the documents during shutdown at Sepangar Bay 100MW Gas Fired Power Plant in Sabah. 2010
33 Suew Gulf Power (Egypt) ExPG Supply and Delivery of Anodes for Cathodic Protection System. 2010
 